ECG releases dumsor timetable [See affected areas]

The ECG says these interruptions in the power supply are to facilitate the work of contractors at various stages and times.

ECG releases dumsor timetable [See affected areas]

The Electricity Company of Ghana (ECG) has released the power outages timetable for Greater Accra for the month of May 2021.

The outages, the ECG has explained is due to ongoing construction works in the power sector especially at the Pokuase Bulk Supply Point.

According to the ECG, as part of projects to improve power supply reliability and system voltages, the Ghana Grid Company (GRIDCo) in collaboration with the ECG are undertaking these interruptions in the power supply to facilitate the work of contractors at various stages and times.

The ECG says requires a complete shutdown of the 330kv line thereby affecting power supply reliability to the Mallam Bulk Supply Point (BSP).

This is because, the new Pokuase Bulk Supply Point, which is near completion and sponsored by the Millennium Challenge Corporation (MCC) under the auspices of the Millennium Development Authority (MiDA) will require a tie-in to GRIDCo's 330kv transmission line.

The outages will rotate between day and night from 6am to 6pm and 6pm to 6am for eight days.

According to the ECG, the tie-in works will take eight days from Monday, May 10 to Monday, May 17, 2021 and will affect power supply to some customers in the North-Eastern parts of Accra.

The ECG has explained that other needed interruptions in power supply to enable contractors complete the different intervention projects, will be communicated in due course.